5 Year Masterplan

2016 - 2020

Schedules

Cleaning and washing of Town Council managed Hawker/Food Centres

Cyclical Maintenance

Works that keep facades in good condition

Upgrading Programmes

NRP and ROS

Maintenance


Cyclical maintenance is carried out to preserve the facades of our buildings and ensure that the fittings and fixtures remain in good condition.The types of cyclical maintenance works carried out by the Town Council include:
 
 
 Repairs and Redecoration
 Reroofing
 Rewiring
 Replacement of Booster and Transfer Pumps
 Replacement of Water Pipes and Tanks
 



 
S/No Project Locations Status Estimated Completion Date
1 Repairs & Redecoration Blocks 484 to 491 Jurong West Ave 1 In progress May-19
2 Repairs & Redecoration Blocks 133 to 139 Bukit Batok West Ave 6 In progress Aug-19
3 Repairs & Redecoration Blocks 101 to 107 Jurong East St 13, Blocks 130 to 135 Jurong Gateway Road In progress Oct-19
4 Repairs & Redecoration Blocks 543 to 559 Jurong West St 42 In progress Feb-20
5 Replacement of sunbreakers and other façade attachments Blocks 357 to 369 Yung An Road / Corporation Drive In progress Jun-19
6 Reroofing Blocks 639, 642 Bukit Batok Central, Blocks 252 to 255 Jurong Est St 24 In progress Apr-19
7 Electrical Rewiring  Blocks 410 to 416 Commonwealth Ave West, Blocks 632 to 634, 636 to 642 Bukit Batok Central, Blocks 105, 107 Jurong East St 13 In progress Sep-19
8 Replacement of Alert Alarm System  Blocks 318A Jurong East Ave 1, Blocks 338B, 339C Kang Ching Road In progress Nov-19
9 Replacement of Refuse Handling Equipment Blocks 297 to 299 Bukit Batok St 22, Blocks 623 to 628 Bukit Batok Central, Blocks 517A, 517C to 517E Jurong West St 52 In progress Sep-19
10 Replacement of HDPE lining to Stainless Steel Water Tanks Blocks 169 to 172, 175 to 178, 180, 182 & 183 Bukit Batok West Ave 8, Blocks 201 to 2145 Bukit Batok St 21, Blocks 515, 516, 518 to 520 Jurong West St 52 In progress Nov-19
11 Replacement of Booster Pumps with Control Panels Blocks 371 to 374 Jurong East St 32, Blk 63 to 66, Blocks 111 to 122, 155, 156, 158 to 163 Yung Kuang Rd / Ho Ching Rd / Corporation Dr / Yung Loh Rd, Blocks 321 to 328, 330, 345 to 355, 357 to 363 & 365 to 369 Tah Ching Rd / Kang Ching Rd / Yung An Rd / Corporation Dr In progress Aug-19
12 Replacement of Booster Pumps with Control Panels Blocks 101 to 103, 105 to 113, 115, 116 Jurong East St 13,  Blocks 209 to 214, 216 to 219, 219A, 220, 221A, 223A, 224, 225A, 226 to 234, 236, 238 to 240 Jurong East St 21, Blocks 241, 243 to 251, 257, 258, 260, 261, 263 & 264 Jurong East St 24, Blocks 317, 318A, 319 to 322, 322A, 323 to 325, 327 & 328 Jurong East Ave 1 / Jurong East St 31 In progress Aug-19






 